What is the average delivery time?
Average Delivery Time by Configuration
Our average on-time delivery rate over 2025 was 94%. The average production and delivery window depends on how much of the chassis is customised.
| Configuration | Average production time | Shipping time | Total to destination port |
|---|---|---|---|
| Standard catalogue model | 12-18 days | 30-45 days (sea) | 42-63 days |
| Part-customised (track width, frame length, interface) | 22-32 days | 30-45 days (sea) | 52-77 days |
| Fully customised (new design, FEA, prototype) | 38-55 days | 30-45 days (sea) | 68-100 days |
| Evaluation unit (air freight) | 12-18 days | 5-10 days (air) | 17-28 days |
What the Averages Include
These figures cover the time from deposit receipt to the vessel departing, and are based on completed orders rather than the fastest ones. They include drawing approval time for customised builds, which typically accounts for 5-10 days of the total depending on the number of review rounds. They do not include the time between the deposit arriving and the drawing being approved, because that depends on how quickly your side responds.
Situations That Extend the Schedule
- Drawing approval rounds - each additional review round adds 3-5 days. Approving with clear, consolidated comments in one pass is the single biggest lever you have on the date.
- Non-standard track chains - special profiles or oversize pitch lengths need procurement and typically add 7-10 days.
- Peak season - orders placed in the weeks before the European construction season, and before the Chinese National Day holiday in early October, need 5-7 days more.
- Custom certification - a new CE or country-specific certification on the documentation side adds 3-5 days of administrative time.
What We Do to Hold the Date
- Production slots are reserved at deposit confirmation, not at the start of the build, so your position in the queue is protected.
- Material for confirmed orders is bought in advance of the build slot, so a supplier delay does not push your shipment.
- Every customised chassis is load tested before dispatch, and the test plus the report takes 2-3 days. We build this into the schedule rather than compressing it.
- If a schedule does slip, we tell you early with a revised date and a recovery plan, not at the shipping deadline.
Planning Around a Project Date
If you have a fixed on-site date, tell us at enquiry stage rather than after ordering. We can usually work backwards from that date and confirm whether a production slot can meet it, and we will be direct if it cannot. The most common successful pattern we see is a 4-6 week buffer between the planned on-site date and the standard lead time, which absorbs customs clearance variability in the destination country - a factor outside our control and outside yours.